works are as following to Buildings 0229/J0762 and 0229/J0753 (see attached Site Plan):
Both Buildings are B Class Asbestos – Bonded. Subcontractor will literally spray with epoxy and remove. No ARCP to be reviewed. Carry out Air Monitoring prior to demolishment of Buildings – Friday 13th September, 2013 Carry out Air Monitoring during the removal of buildings – Monday 16th September, 2013 Carry out Air Monitoring after the removal of buildings – Tuesday 17th September, 2013 Supply a report to capture Air Monitoring data.
Complete DCT requirement. ALL OF THE ABOVE WORKS ARE TO BE COMPLETED IAW WITH ASBESTOS MANAGEMENT PLAN (as previously issued)
Work Requests are as follows:
Building 0229/J0762 140228076
Building 0229/J0753 140228077
==
Contractor: Garith Jackson 0434 807 844
==
Air monitoring prior to being demolished was completed on Friday the 13th;
Air monitoring during strip out going ahead as planned on Tuesday the 10th.