Mount Isa Hospital C-Block

Inspection in relation to the 3rd phase of asbestos removal of C-Block conducted Tuesday the 6th August 2012. Identified issue with two of the recent four areas where ACM on pipework removed. Ground floor store rooms required further make safe and clean, together with further fibre count testing, and two tape tests after wet wipe of entire surface areas of subject rooms.

Work to date in relation to 3rd phase, C-Block (July 2013):

  • Thursday 4th (8 hrs);
  • Friday 5th (8 hrs);
  • Saturday 6th (8 hrs);
  • Sunday 7th (8 hrs);
  • Monday 8th (8 hrs);
  • Tuesday 9th (8 hrs);
  • Wednesday 10th (8 hrs);
  • Thursday 11th (8 hrs);
  • Friday 12th (8 hrs);
  • Saturday 13th (8 hrs);
  • Sunday 14th (8 hrs);
  • Monday 15th (8 hrs);
  • Tuesday 16th (8 hrs);
  • Wednesday 17th (8 hrs);
  • Thursday 18th (4 hrs);
  • Saturday 20th (4 hrs);
  • Tuesday 23rd (4 hrs);
  • Wednesday 24th (4 hrs);
  • Thursday 1st (4 hrs);
  • Tuesday 6th (4 hrs);
  • Tuesday 13th (4 hrs);
This entry was posted in Remploy. Bookmark the permalink.